End
Current

Civil engineering and level crossing works undertaken as part of the resignalling between Coventry and Nuneaton.

Client: Atkins

VGC contract value: £3 million

Key features:

  • Over 9km of route replaced
  • Night time and weekend possession working
  • Three types of piled foundations used.